TWO of the four operating theatres at the hospital are back in use.

Published
At around 5pm yesterday the heat exchanger in the air conditioning unit located in the plant room above the main theatres of the PEH failed causing water damage to the theatres below and forcing their closure. (23040660)

Staff worked through the night to cope with water damage after a heat exchanger unit above the theatres failed.

They were all shut at around 5pm, with two patients having to be safely taken back to the ward from operations.

The fault has been fixed.

As at 1pm today theatres one and two were back in action having been deep cleaned and re-commissioned.

The Theatre in Day Patient Unit is being held as an emergency theatre for any obstetric cases until at least 6pm this evening.

All four theatres will be back in action for all planned admissions which commence at 7am tomorrow.